Several Schemes of Efficient Integration of Design and Construction of Modular Changsha Makeshift Hospital Based on EPC Management Thinking

Received: 21 November 2022     Accepted: 22 December 2022     Published: 28 December 2022
Views:       Downloads:
Abstract

In recent years, the environment of the entire construction industry has undergone subversive changes due to social supply and demand, and the EPC general contract management mode has gradually emerged the top-level design of the industry. Furthermore, the outbreak of COVID-19 in our country at the end of 2019 has lasted for nearly three years, the world's public health security is facing great challenges. This paper discusses the main reasons for the sharp contraction of the construction industry in recent 10 years, and reveals the shortcomings of the construction industry in inter-professional coordination and rapid construction of epidemic prevention and control. In combination with the construction and research of Changsha makeshift Hospital, the research group proposed the architectural design concept of "box-mold combination" to achieve the standardization of architectural design and the modularization of factory production. An integrated design process of architectural design and construction has been established, a team of design and research institute has been specifically set up, and a five-dimensional BIM+ three-part joint review integrated management system has been put forward, which makes up for the shortcomings of single implementation of the general construction contract. At the same time, the modular integral sanitary ware combination and installation process are adopted, and the points for attention in the assembly integral sanitary ware installation are given.

Published in Science Discovery (Volume 10, Issue 6)
DOI 10.11648/j.sd.20221006.33
Page(s) 528-533
Creative Commons

This is an Open Access article, distributed under the terms of the Creative Commons Attribution 4.0 International License (http://creativecommons.org/licenses/by/4.0/), which permits unrestricted use, distribution and reproduction in any medium or format, provided the original work is properly cited.

Copyright

Copyright © The Author(s), 2022. Published by Science Publishing Group

Keywords

EPC General Contracting Management, COVID-19, "Box Mold Combination", Five-Dimensional BIM, Three-Part Joint Review

References
[1] 陆秋琴, 竹嘉欣, 黄光球. 建筑企业绿色化发展影响因素研究 [J]. 经营与管理: 1-19.
[2] 魏保平. FIDIC银皮书与我国新版工程总承包合同示范文本的索赔管理比较研究 [J]. 建筑经济, 2022, 43 (S1): 674-678.
[3] 刘俊颖. 国际工程EPC项目风险管理 [M]. 北京: 中国建筑工业出版社, 2017.
[4] 陈戊荣, 陈兆荣, 苏运升, 李雯琪, 尹烨, 温丽娟, 李若羽, 陈唯军. 核酸检测实验室建筑关键技术发展研究 [A]. 《施工技术 (中英文)》杂志社、亚太建设科技信息研究院有限公司. 2022年全国工程建设行业施工技术交流会论文集 (下册) [C]. 《施工技术 (中英文) 》杂志社、亚太建设科技信息研究院有限公司: 施工技术编辑部, 2022: 628-632.
[5] 陈戊荣, 陈兆荣, 苏运升, 李雯琪, 尹烨, 李若羽. 充气膜结构病毒检测实验室建造全过程工程实践 [A]. 《施工技术 (中英文)》杂志社、亚太建设科技信息研究院有限公司. 2022年全国工程建设行业施工技术交流会论文集 (下册) [C]. 《施工技术 (中英文) 》杂志社、亚太建设科技信息研究院有限公司: 施工技术编辑部, 2022: 820-823.
[6] 陈戊荣, 陈兆荣, 苏运升, 李雯琪, 尹烨, 温丽娟, 李若羽, 陈唯军. 气膜性建筑结构核酸检测实验室的创新设计研究 [J]. 建筑结构, 2022, 52 (S1): 698-703.
[7] 苏运升, 陈戊荣, 陈兆荣, 程希寒. 应急防疫气膜系统设计研究与实践 [J]. 装饰, 2022, (08): 12-16.
[8] 陈戊荣, 陈兆荣, 苏运升, 李雯琪, 尹烨, 李若羽. 超短临时建筑核酸检测实验室设计若干技术研究 [J]. 建筑结构, 2022, 52 (S1): 704-708.
[9] 陈戊荣, 陈兆荣, 苏运升, 李雯琪, 尹烨, 李若羽. 快速建造下的科技抗疫气膜版火眼实验室工程化标准式研究 [A]. 《施工技术 (中英文)》杂志社、亚太建设科技信息研究院有限公司. 2022年全国工程建设行业施工技术交流会论文集 (下册) [C]. 《施工技术 (中英文)》杂志社、亚太建设科技信息研究院有限公司: 施工技术编辑部, 2022: 617-622.
[10] 张方琪, 刘海潮, 屈磊, 杨亚伟, 翁雁鸣, 方瑶. 上海会展中心方舱医院新型冠状病毒奥密克戎变异株感染者临床分析 [J]. 中国热带医学: 1-8.
[11] 梁东, 刘洁. 方舱医院给排水设计要点 [J]. 重庆建筑, 2022, 21 (10): 13-15.
[12] Li Wenqi, Chen Wurong, Chen Zhaorong, Su Yunsheng, Cai Zhili, Yin Ye, Li Ruoyu. The Building Structure of the New Crown Nucleic Acid Testing Laboratory Was Quickly Constructed Several Program Studies [J]. Science Discovery, 2022, 10 (4).
[13] Chen Wurong, Su Yunsheng, Chen Zhaorong, Li Wenqi, Yin Ye, Wen Lijuan, Li Ruoyu, Chen Weijun. Innovative Practice of Key Technologies in Nucleic Acid Detection Laboratory of Gas Membrane Building Structure [J]. Science Discovery, 2022, 10 (1).
[14] Cai Zhili, Zhang Jichao, Chen Zhaorong, Chen Wurong, Ke Biaozhi, Zeng Changluo. Exploration on the Integration of Integrated Design and Construction of Prefabricated Assembly from the Perspective of EPC Management [J]. Science Discovery, 2022, 10 (4).
[15] Chen Zhaorong, Cai Zhili, Zeng Changluo, Bai Zhongkui, Du Shishuai. Seismic Isolation Technology Based on Green Building in Prefabricated Assembly Research Application in Structure [J]. Science Discovery, 2021, 9 (6).
[16] 隋岩鹏, 陈英杰. 装配式轻钢结构活动板房在武汉火神山医院建设中的应用 [J]. 建筑经济, 2020, 41 (07): 118-120.
[17] 袁理明, 侯国求, 罗海兵, 武永光. 武汉雷神山医院结构设计 [J]. 建筑结构, 2020, 50 (08): 1-8.
[18] 设计施工一体化是企业数智化转型的核心引擎 [J]. 中国建设信息化, 2022, (20): 22-23.
[19] 刘书鹏, 黎伟财, 叶浩, 郑昊. 装配式混凝土建筑全过程设计和审查管理的要点分析 [J]. 建筑结构, 2022, 52 (S1): 1702-1706.
[20] 陈立. 钢结构幕墙一体化设计施工技术 [J]. 建筑施工, 2021, 43 (09): 1801-1803.
Cite This Article
  • APA Style

    Chen Zhaorong, Liao Fei, Lv Jiping, Cai Zhili, Chen Wurong, et al. (2022). Several Schemes of Efficient Integration of Design and Construction of Modular Changsha Makeshift Hospital Based on EPC Management Thinking. Science Discovery, 10(6), 528-533. https://doi.org/10.11648/j.sd.20221006.33

    Copy | Download

    ACS Style

    Chen Zhaorong; Liao Fei; Lv Jiping; Cai Zhili; Chen Wurong, et al. Several Schemes of Efficient Integration of Design and Construction of Modular Changsha Makeshift Hospital Based on EPC Management Thinking. Sci. Discov. 2022, 10(6), 528-533. doi: 10.11648/j.sd.20221006.33

    Copy | Download

    AMA Style

    Chen Zhaorong, Liao Fei, Lv Jiping, Cai Zhili, Chen Wurong, et al. Several Schemes of Efficient Integration of Design and Construction of Modular Changsha Makeshift Hospital Based on EPC Management Thinking. Sci Discov. 2022;10(6):528-533. doi: 10.11648/j.sd.20221006.33

    Copy | Download

  • @article{10.11648/j.sd.20221006.33,
      author = {Chen Zhaorong and Liao Fei and Lv Jiping and Cai Zhili and Chen Wurong and Su Yunsheng and Ke Biaozhi},
      title = {Several Schemes of Efficient Integration of Design and Construction of Modular Changsha Makeshift Hospital Based on EPC Management Thinking},
      journal = {Science Discovery},
      volume = {10},
      number = {6},
      pages = {528-533},
      doi = {10.11648/j.sd.20221006.33},
      url = {https://doi.org/10.11648/j.sd.20221006.33},
      eprint = {https://article.sciencepublishinggroup.com/pdf/10.11648.j.sd.20221006.33},
      abstract = {In recent years, the environment of the entire construction industry has undergone subversive changes due to social supply and demand, and the EPC general contract management mode has gradually emerged the top-level design of the industry. Furthermore, the outbreak of COVID-19 in our country at the end of 2019 has lasted for nearly three years, the world's public health security is facing great challenges. This paper discusses the main reasons for the sharp contraction of the construction industry in recent 10 years, and reveals the shortcomings of the construction industry in inter-professional coordination and rapid construction of epidemic prevention and control. In combination with the construction and research of Changsha makeshift Hospital, the research group proposed the architectural design concept of "box-mold combination" to achieve the standardization of architectural design and the modularization of factory production. An integrated design process of architectural design and construction has been established, a team of design and research institute has been specifically set up, and a five-dimensional BIM+ three-part joint review integrated management system has been put forward, which makes up for the shortcomings of single implementation of the general construction contract. At the same time, the modular integral sanitary ware combination and installation process are adopted, and the points for attention in the assembly integral sanitary ware installation are given.},
     year = {2022}
    }
    

    Copy | Download

  • TY  - JOUR
    T1  - Several Schemes of Efficient Integration of Design and Construction of Modular Changsha Makeshift Hospital Based on EPC Management Thinking
    AU  - Chen Zhaorong
    AU  - Liao Fei
    AU  - Lv Jiping
    AU  - Cai Zhili
    AU  - Chen Wurong
    AU  - Su Yunsheng
    AU  - Ke Biaozhi
    Y1  - 2022/12/28
    PY  - 2022
    N1  - https://doi.org/10.11648/j.sd.20221006.33
    DO  - 10.11648/j.sd.20221006.33
    T2  - Science Discovery
    JF  - Science Discovery
    JO  - Science Discovery
    SP  - 528
    EP  - 533
    PB  - Science Publishing Group
    SN  - 2331-0650
    UR  - https://doi.org/10.11648/j.sd.20221006.33
    AB  - In recent years, the environment of the entire construction industry has undergone subversive changes due to social supply and demand, and the EPC general contract management mode has gradually emerged the top-level design of the industry. Furthermore, the outbreak of COVID-19 in our country at the end of 2019 has lasted for nearly three years, the world's public health security is facing great challenges. This paper discusses the main reasons for the sharp contraction of the construction industry in recent 10 years, and reveals the shortcomings of the construction industry in inter-professional coordination and rapid construction of epidemic prevention and control. In combination with the construction and research of Changsha makeshift Hospital, the research group proposed the architectural design concept of "box-mold combination" to achieve the standardization of architectural design and the modularization of factory production. An integrated design process of architectural design and construction has been established, a team of design and research institute has been specifically set up, and a five-dimensional BIM+ three-part joint review integrated management system has been put forward, which makes up for the shortcomings of single implementation of the general construction contract. At the same time, the modular integral sanitary ware combination and installation process are adopted, and the points for attention in the assembly integral sanitary ware installation are given.
    VL  - 10
    IS  - 6
    ER  - 

    Copy | Download

Author Information
  • China Construction Fifth Engineering Bureau the Third Construction Co., Ltd., Changsha, China

  • China Construction Fifth Engineering Bureau the Third Construction Co., Ltd., Changsha, China

  • China Construction Fifth Engineering Bureau the Third Construction Co., Ltd., Changsha, China

  • China Construction Fifth Engineering Bureau the Third Construction Co., Ltd., Changsha, China

  • BGI Genomics Co., Ltd, Shenzhen, China

  • College of Design and Innovation, Tongji University, Shanghai, China

  • China Construction Fifth Engineering Bureau the Third Construction Co., Ltd., Changsha, China

  • Sections